Business Oregon Echo Levy Project

Granting Agency: Business Oregon
Award Amount: $114,400
Project Start Date: Spring 2023
Projected End Date: Q3 2025
Primary Entity: City of Echo
Project Description: A project scope is currently being developed for a levy system that will protect the city of Echo from flooding events. Anderson and Perry will be completing the scope and budget estimate for the levy design.
Next Steps: A&P are currently working through the SOW.
Project Timeline | Q3 2023 | Q4 2023 | Q1 2024 | Q2 2024 | Q3 2024 | Q4 2024 | Q1 2025 | Q2 2025 | Q3 2025 | Q4 2025 |
---|---|---|---|---|---|---|---|---|---|---|
SOW and Budget Development | X | |||||||||
SOW and Budget Submission | X | |||||||||
Application Submission | X | |||||||||
If Awarded - Study, Design, and Permits | X | X | X | |||||||
Funding Search for Implementation | X | X | X | |||||||
Implementation | X | X | X | X | X | X |